The Kenya National Highways Authority (KeNHA) has unveiled plans to construct 25 new feeder roads connecting estates across Kiambu County to the 16.5-kilometer Nairobi Western Bypass (Gitaru–Ruaka).
In a tender document dated July 20, KeNHA detailed that the project will upgrade selected road links across Kiambu County to bitumen standards under the Construction of Feeder Roads along Western Bypass Road Project (Tender No. KeNHA/2980/2026), funded through the Government of Kenya Development Fund.
“Construction Authority (NCA) in Category 1 or equivalent for foreign contractors (however, the successful tenderer shall register with the NCA before the signing of the contract) for the CONSTRUCTION OF FEEDER ROADS ALONG WESTERN BYPASS ROAD PROJECT to be funded through the Government of Kenya Development Fund,” the document read in part.
25 Feeder Roads Planned Under the Nairobi Western Bypass Project
The following road links have been identified for upgrading to bitumen standard under the KeNHA project:
- Roselyne – Kang’ururi – Slaughter Road (1.6 km)
- Slaughter – Gituamba – Gacharage Road (1.5 km)
- Lily of Valley – Muya – Kagondo Road (1.5 km)
- Lily of Valley – Muya – Christco Road (1.2 km)
- Yamogo – Sacred Heart Road (3.5 km)
- Gatwikira Road (1.5 km)
- Kimachia / Mbari ya Njau (1.3 km)
- Riverside – King’eero SDA (1.8 km)
- Marugu Road (1.1 km)
- ACK St. Mark Tito Road (1.1 km)
- Karura – Kanyungu Road (1.0 km)
- Cura / Gatumumu Road (1.4 km)
- Rungiri Primary – PCEA Road (1.0 km)
- Ndongoro / Kahingaru Road (1.5 km)
- Rukubi Kwa Mbau Road (1.0 km)
- Rubby / Gitaru Road (1.0 km)
- Ruthiboi / Kanyariri Road (1.0 km)
Also Read:Â Win for KeNHA as Court Allows Tarmac Upgrade Through Aberdare National Park Forest
Details and Construction Timelines for the 25 Feeder Roads
From the KeNHA tender document, the construction of the 25 feeder roads planned under the Nairobi Western Bypass project is expected to take 36 months (three years) to complete.
The Nairobi Western Bypass project involves upgrading the roads to bitumen standard, with a 7-meter-wide carriageway and 1.5-meter shoulders on both sides.
Plans also include drainage works such as side ditches, box culverts and pipe culverts, together with the installation of road signs, thermoplastic markings, raised curbs, guardrails and zebra crossings.
After completion, the contractor will be required to maintain the roads during a 24-month defects notification period.
Construction is scheduled to take place on weekdays between 8:00 a.m. and 5:00 p.m. and Saturdays from 8:00 a.m. to 12:00 noon.
Also Read:Â KeNHA Announces 30-Day Traffic Disruption at Coptic Roundabout
The Nairobi Western Bypass (Gitaru–Ruaka)
The Nairobi Western Bypass (Gitaru–Ruaka) is the fourth and final section of Nairobi’s ring-road network, built to divert through-traffic from the city center and ease congestion along the Nairobi–Nakuru corridor.
This bypass starts at Gitaru, near Kikuyu town, where it connects to the Nairobi Southern Bypass and the Nairobi–Nakuru highway, and ends at Ruaka, where it connects to the Nairobi Northern Bypass.
Stretching approximately 16.5 kilometres, the road passes through Gitaru, Wangige, Kihara, Ndenderu, Rumenyi and Ruaka, with more than 17 kilometres of service roads constructed alongside the main carriageway.
The dual carriageway features major interchanges, service roads, pedestrian walkways, cycle tracks in selected sections, pedestrian crossings, noise barriers, improved drainage systems and a bus park at Wangige.